THE rehabilitation of the collapsed section of the highway at Mosquito Creek in South Trinidad is 43% completed, with repair works scheduled to be finished by May 12.
This according to the National Infrastructure Development Company (Nidco).
Responding to questions from the Sunday Express last week, the State agency said it had commenced stabilisation and restoration works in March 2025.