By Mark DaCosta- A some 45-hour blackout in East Berbice-Corentyne has reportedly ended in stages, and it has raised hard questions about how reliable our national electricity system really is. The failure of a single substation at Canefield, a facility Guyana renovated at great public expense, left thousands of Region Six households and businesses without power for nearly two days. The authorities’ thin communication during the crisis made matters worse.
Trouble began around midday on Thursday, 19 November. Technicians at Guyana Power and Light (GPL) were re-energising the Canefield substation when a flash erupted from a switchgear cubicle. GPL later traced the fault to failed insulation in the panel housing the grounding transformer. That device allows protective systems to detect and isolate faults, so the station could not safely be returned to service. Several defective components had to be replaced and the equipment retested, experts tell this publication.



Public patience was tested further when GPL’s Saturday deadline of 1 p.m. passed unmet. The utility conceded shortly before that hour that it could not deliver. Into that vacuum came a doctored social media post, made to resemble an official notice, promising power on 22 or 23 November. GPL rejected it as fake, but the episode showed how quickly rumour fills a silence.
Continues on Village Voice
The portable companion to gazettE. Get notifications, track read articles, and more. The latest news from Trinidad and Tobago, in one place.
Related stories
See articles related to "45-Hour Berbice Blackout Exposes Critical Weaknesses in Guyana’s Power Grid"