With completion targeted for the last quarter of 2026, the new $880 million Charity Market Multipurpose Wharf, which is being constructed by S Jagmohan Construction and General Supplies Inc, is about 30 per cent complete.
According to the Public Works Ministry on Friday, substantial progress has been made on the core infrastructure, with the reinforced concrete jetty section of the wharf now largely completed.
The Ministry added that the contractor is presently preparing to cast the remaining four-inch concrete top-up slab to finalise the jetty deck. Simultaneously, work has progressed on the next critical phase, with the driving of precast concrete piles for the jetty head section of the wharf structure currently underway.