Energy Minister Dr Roodal Moonilal is hailing a major acceleration in natural gas production from BP Trinidad and Tobago’s Cypre subsea project, describing it as a milestone for the country’s energy supply.
The Cypre development, comprising seven wells, had its first gas output in March 2025 after Phase 1, which included four wells. Yesterday, the remaining three wells of Phase 2 went online, significantly ahead of schedule.
Originally slated for 2026, Phase 2 gas production was accelerated in collaboration with the Ministry of Energy and Energy Industries (MEEI).