(Kaieteur News) – More than three years after a contract was signed for the construction of the Belle Vue Pump Station in Region 3, the project remains incomplete with its completion date pushed to May 31, 2027, according to the Auditor General’s 2025 report. Awarded by the National Procurement and Tender Administration Board in the sum of $870.563 million against an engineer’s estimate of $779.199 million, the project saw no payments made during the period under review, though amounts totaling $160.894 million were paid during prior years. The firm, Tepui Group Inc. is headed by Mikhail Rodrigues known as `Guyanese Critic’.
Audit examination and a physical verification carried out on September 2, 2026 revealed a series of irregularities surrounding the contract and its execution. An initial award made on August 14, 2023 for $865.544 million, matching the contractor’s bid form and priced bills of quantities, was rescinded before a second award was made on September 15, 2023 to the same contractor for $870.564 million, which was $5.020 million higher than the sum in the contractor’s bid and aligned with a National Drainage and Irrigation Authority procurement department priced bills of quantities seen in the contract. Auditors also found that the contractor failed to satisfy nine out of the eighteen requirements set out in the evaluation criteria.
Contract records show the agreement was signed on September 22, 2023 for an eighteen-month completion period, yet Addendum No. 1, increasing the advance payment percentage from 15 percent to 30 percent, was dated September 21, 2023, one day before the contract was signed. Addendums No. 2 and No. 3 addressed paying the contractor for materials on site and shifting the contract start date from October 6, 2023 to January 29, 2024, while the National Procurement and Tender Administration Board approved an addendum on June 13, 2025 for an assignment of the contract to another contracting firm. When auditors conducted their physical verification on September 2, 2026 under the assigned firm, an approved completion date of June 16, 2026 had already elapsed and a new completion date of May 31, 2027 had been granted, with excavation, earthworks, and timber piling for the sluice foundation slab underway and no significant works completed after three years.
Continues on Kaieteur News
The portable companion to gazettE. Get notifications, track read articles, and more. The latest news from Trinidad and Tobago, in one place.
Related stories
See articles related to "Audit flags price hikes, addendums and missed deadlines at Belle Vue pump station"